The sanitary waste landfill No. 01 (Hoa Phu - Long Ho commune) has the capacity of about 86,000 tons of garbage, but the volume of garbage received so far is about 135,000 tons, leading to overload of garbage of about 8m. with pavement
The amount of leaked water in the ponds around the landfill is quite large, the water level is about 20-30 cm from the top of the dyke, can spill out.
Facing this situation, the People's Committee of Vinh Long province has approved the investment project of sanitary waste landfill No. 02 with an investment scale of about 2 hectares, ensuring service for about 2.5 years (capable of holding waste for up to five years). 2018).
Currently, after more than one month of construction, landfill No. 02 has completed the bottom layer. Accordingly, geotechnical materials including geotextile, HDPE membrane and GCL composite have been completed phase 01 of the project.
Materials continue to be collected at the site, ready for construction in the next stage.
Land burial 02 with the total investment of about VND 20 billion invested by Vinh Long Public Works Joint Stock Company. AT & T supplies materials and construction works for waterproofing works.